Contract Value
₹5.8 Cr
Hospitality
Cost Incurred
₹3.99 Cr
69% of budget
Built-up Area
51K sqft
Hyderabad, Telangana
Timeline
15 Aug 2026
Started 18 Aug 2025
Project Health
On TrackOverall completion82%
Budget consumed69%
Manager
Vikram Nair
Client
Orchid Hospitality
Recce Due
02 Sep 2025
Delivery Team
4 membersVN
Vikram Nair
Project Manager
AR
Arjun Reddy
Team Member
IS
Imran Shaikh
Team Member
SR
Sandeep Rao
Team Member
| Issue | Location | Trade | Assigned To | Severity | Status |
|---|---|---|---|---|---|
| Tile level mismatch near lift lobby | Level 5 — Lobby | Flooring | Marigold Interiors | Major | In Progress |
| Paint patch mismatch on corridor wall | Level 4 — Corridor | Painting | Marigold Interiors | Minor | Open |
| Door hardware loose — room 512 | Level 5 — Room 512 | Carpentry | Cubicle India | Minor | Closed |