StatusExecution In Progress
Contract Value
₹9 Cr
Commercial
Cost Incurred
₹5.84 Cr
65% of budget
Built-up Area
42K sqft
Mumbai, Maharashtra
Timeline
20 Sep 2026
Started 04 Nov 2025
Project Health
On TrackOverall completion64%
Budget consumed65%
Manager
Vikram Nair
Client
Zenith Retail Ltd.
Recce Due
20 Nov 2025
Delivery Team
5 membersVN
Vikram Nair
Project Manager
PD
Priya Deshmukh
Team Member
AR
Arjun Reddy
Team Member
IS
Imran Shaikh
Team Member
KM
Kavya Menon
Team Member
Total Activities
10
Not Started
3
In Progress
1
Completed
6
Schedule Progress
65%
Status
On Schedule
Planned End
20 Sep 2026
| WBS | Activity | Planned Start | Planned End | Status | Timeline |
|---|---|---|---|---|---|
| 1 | Site Preparation | 10 Feb 2026 | 05 Mar 2026 | Completed | |
| 1.1 | Clearing and Grubbing | 10 Feb 2026 | 18 Feb 2026 | Completed | |
| 1.2 | Leveling and Grading | 16 Feb 2026 | 26 Feb 2026 | Completed | |
| 1.3 | Surveying | 20 Feb 2026 | 05 Mar 2026 | Completed | |
| 2 | Foundation Work | 02 Mar 2026 | 10 Apr 2026 | Completed | |
| 2.1 | Excavation | 02 Mar 2026 | 18 Mar 2026 | Completed | |
| 2.2 | PCC & Footing | 15 Mar 2026 | 10 Apr 2026 | Completed | |
| 3 | Structure | 06 Apr 2026 | 05 Jun 2026 | In Progress | |
| 3.1 | Column Casting | 06 Apr 2026 | 05 May 2026 | Completed | |
| 3.2 | Slab Work | 28 Apr 2026 | 05 Jun 2026 | In Progress | |
| 4 | Finishing | 25 May 2026 | 20 Aug 2026 | Not Started | |
| 4.1 | Flooring | 25 May 2026 | 30 Jun 2026 | Not Started | |
| 4.2 | False Ceiling | 15 Jun 2026 | 25 Jul 2026 | Not Started | |
| 4.3 | Painting & Handover | 10 Jul 2026 | 20 Aug 2026 | Not Started |